U.S. EMBASSY BERLIN, CLAY ALLEE CAMPUS

PROJECT LOCATION: Zehlendorf (Berlin), GERMANY
PROJECT DEFINITION: Construction of U.S. Embassy Campus
OWNER: U.S. Bureau of Overseas Building Operations
CONTRACTOR: Pernix Germany GmbH
DURATION: 16 Months / 2018 - 2019
SCOPE OF WORK: -Major rehabilitation works;
-Modernization of campus security and planning MSGQ (Marina Security Guard Headquarters) for the US Embassy.
Image

U.S. EMBASSY COLOMBO (SRI LANKA)

PROJECT LOCATION: Colombo, SRI LANKA
PROJECT DEFINITION: Construction of U.S. Embassy Campus
OWNER: U.S. Bureau of Overseas Building Operations
CONTRACTOR: Caddell Construction Co. Inc
DURATION: 24 Months / 2016 - 2018
SCOPE OF WORK: Execution of Reinforced Concrete works of All Campus.
Image

MONS RAILWAYSTATION (BELGIUM)

PROJECT LOCATION: Mons, BELGIUM
PROJECT DEFINITION: Construction of New Mons Railway Station.
OWNER: Eurogare
CONTRACTOR: S.M. Cit Blaton-CFE-BPC Hainaut, Metal Yapi
DURATION: 18 Months / 2017 - 2018
SCOPE OF WORK: 5600 tons of steel erection works including assembly on site.
Image

MALL OF THE NETHERLANDS DEN HAAG, NETHERLANDS

PROJECT LOCATION: Leidschendam, Den Haag, NETHERLANDS
PROJECT DEFINITION: Construction of Shopping Mall
OWNER: Unibail Rodamco (UBR)
CONTRACTOR: Ballast Nedam
DURATION: 12 Months / 2018
SCOPE OF WORK: -Execution of Formwork;
-Concrete and placement of Precast units in Parking Block (43.000 sqm).
Image

HART VAN ZUID INTERNATIONAL CONFERENCE CENTER, NETHERLANDS

PROJECT LOCATION: Ahoi 10 road Rotterdam, Netherlands
PROJECT DEFINITION: Construction of Conference Center
OWNER: Hart Van Zuid
CONTRACTOR: Ballast Nedam, Heijmans
DURATION: 12 Months / 2018 - 2019
SCOPE OF WORK: -Execution of Formwork;
-Concrete placement of Precast units (25.000sqm).
Image