Hart Van Zuid International Conference Center (The Netherlands)


Project Location: Ahoi 10 road Rotterdam, Netherlands
Project Definition: Construction of Conference Center
Owner: Hart Van Zuid
Contractor: Ballast Nedam, Heijmans
Duration: 12 Months / 2018 - 2019
Scope of Work: -Execution of Formwork;
-Concrete placement of Precast units (25.000sqm).
6